Tiwi Land Council
Work progress
Homeland/s | Service Provider/Contractor | Proposed Work | Grant Value (excluding GST) | Current Status | Completion Reports |
---|---|---|---|---|---|
Paru - Stage 1 | Tiwi Islands Regional Council | Housing and Infrastructure Upgrades | $250,000 | Complete October 2023 | HHIP - Paru Project - Stage 1 - Completion report |
Paru - Stage 2 | Tiwi Islands Regional Council | Housing and Infrastructure Upgrades | $540,000 | Works commence March 2024 | No Report |